Ružomberok D1 bypass opened after major redesign and permit delays

Postoj reports that nine geological surveys failed to identify the slope-instability risk that later forced a substantial redesign and years of waiting for new permits.

Live Version: 5Sources: 10Perspectives: 2Updated:
Foto: TASR · source

What's new

  • Postoj reported that nine geological surveys for NDS did not reveal the risk of slope instability.
  • According to the outlet, the landslide risk required a major redesign and several years of waiting for new permits.
  • Postoj estimates that the final cost is likely about three times the original contract price.

The D1 Hubová–Ivachnová bypass around Ružomberok is operating in both directions after 13 years of construction. Postoj reported that nine geological surveys for NDS had failed to identify a slope-instability risk that subsequently required a substantial redesign and several years of waiting for new permits. The outlet estimates that the final cost is likely about three times the original contract price.124

Opening procedure

The Hubová–Ivachnová section was ceremonially opened on Oct. 5. Denník N reported that the moderator joked during the ribbon-cutting that one pair of scissors was missing, leaving Transport Minister Jozef Ráž without scissors.7

The first motorists entered the section on Monday evening. Aktuality.sk reported that motorway crews opened it first towards Liptovský Mikuláš and then towards Žilina; it is now operating in both directions. NDS urged drivers to pay close attention to changed traffic signs, particularly at the Ivachnová interchange.1358

Hospodárske noviny tested the bypass among the first users and measured a time saving on the new route. NDS says the usual time saving may reach approximately 16 minutes and several dozen minutes during traffic peaks.6

Route through the Váh valley

The motorway begins at the grade-separated Hubová junction, where it links with the I/18 road. It crosses the Váh river, follows the valley’s northern side and passes through Hrboltová, a district of Ružomberok. The route then reaches the Likava junction, passes through the Čebrať tunnel and continues near Likava.56

From there, the motorway follows a northern bypass of Martinček and Lisková before crossing the Váh for a second time. At Ivachnová, it joins the existing four-lane motorway in the direction of Košice. The project also directly adjoins the planned D1 section between Turany and Hubová towards Martin.56

Traffic and local effects

The section contains 19 bridges and three junctions. TASR, Pravda and Hospodárske noviny put the Čebrať tunnel’s length at 3.6 kilometres, while Aktuality.sk reports 3.3 kilometres. By moving transit vehicles away from streets in Ružomberok, the bypass is expected to reduce dense traffic and residents’ exposure to traffic-related noise and smog.1235

NDS says the bypass may reduce ordinary travel time by about 16 minutes compared with the existing route through Ružomberok. During peak traffic, the saving may reach several tens of minutes.158

A 13-year, redesigned project

Construction began in 2013 and was originally due to finish in 2017. STVR reported that a major landslide stopped work and forced a route change, extending the Čebrať tunnel from two kilometres to more than 3.6 kilometres. Postoj said nine geological surveys for NDS had failed to identify the slope-instability risk and that the resulting redesign required several years of waiting for new permits. Full construction resumed in 2018, and the tunnel was bored through in both directions in 2022.24

The project’s final cost remains unclear. Postoj reported an original contract price of €227 million, contracts and amendments in the central register totalling €335 million, and a 2026 construction schedule listing €753 million excluding VAT. The outlet estimates that the final sum is likely about three times the original contract price. It also reported that a government audit found contract-publication and financial-discipline violations and that the motorway company was fined.4

Why it matters

The bypass moves transit traffic out of Ružomberok and connects to the existing four-lane motorway towards Košice. Hospodárske noviny reported that its opening creates a continuous 200-kilometre motorway stretch from Hubová to Košice, while STVR said Turany–Hubová remains the missing D1 section between Bratislava and Košice and could become a traffic bottleneck.256

Related stories

Version history

  1. version 5 · New reporting says undetected slope-instability risk forced a major redesign and years of permit delays, while the final cost is estimated at roughly three times the original contract price.
  2. version 4 · Hospodárske noviny has now tested the bypass among the first users, while new reporting details how its two directions were opened in sequence.
  3. version 3 · The first motorists have now used the bypass in both directions, and NDS has warned drivers to follow changed signs near Ivachnová.
  4. version 2 · The bypass has now been ceremonially opened and opened to motorists, with new reporting detailing its 13-year construction, landslide-driven redesign and unresolved final cost.
  5. version 1 ·